Silex / Project Risk Snapshot

One missing pump threatens commissioning.

Stonefield water upgrade

Week 4 · Tuesday, 09:00

A dependency view for the project manager before the weekly schedule review.

Situation

The fictional pump supplier moves its dispatch estimate beyond the planned installation window. The test crew is still booked against the old sequence.

Decision supported

Validate the revised delivery date before retaining the test crew booking or proposing a new commissioning date.

Dependency chain

Dispatch estimate
Week 6
Installation
Was Week 5
Testing
Booked Week 6

Risk register

Qualitative exposure, not a probability score
DependencyAssessmentOwner / next check
Pump arrivalHigh milestone exposure: the current sequence cannot be supported by the supplier estimate.Procurement: obtain transport and arrival confirmation by Wednesday noon.
Test crewWatch: the reservation may no longer align with installation readiness.Project manager: check booking flexibility before changing dates.
AccessNo new timing conflict identified in the demo permit record.Site lead: verify work scope and conditions.

Decision gate

Do not publish a replacement commissioning date until arrival, installation duration and test-crew availability have been reconciled. The snapshot identifies exposure; it does not establish an actual delay duration.

Confidence and limits

High that the plan contains a dependency conflict; low on the eventual commissioning date until transport and installation timing are confirmed.

Evidence register — all records invented

Scenario evidence and source limitations
Record / cut-offScenario informationSource quality / limitation
SF-01 / Mon 16:00Supplier email estimates dispatch in Week 6; the schedule expects installation in Week 5.Direct demo correspondence; not a confirmed delivery appointment.
SF-02 / Tue 08:00Commissioning crew booking remains in Week 6.Current demo booking; rescheduling terms not yet checked.
SF-03 / Mon 12:00Access permit recorded as issued through Week 7.Demo permit copy; scope must still match planned work.