Silex / Periodic Assessment
Permits improved. Acceptance capacity is now the constraint.
Orchard Connect expansion
End of demo Month 2 · Next 30 days
A forward-looking review for the executive and program sponsor.
Situation
Two demo permit dependencies closed during the month. Three work packages now seek acceptance in the same week, while only one test team is confirmed.
Decision supported
Agree a handover sequence with the acceptance lead; validate additional capacity before advancing customer commitments.
What changed across the period
| Area | Start of month | Current assessment |
|---|---|---|
| Permit dependencies | Two open items in the reviewed set. | Both recorded as closed; exposure reduced for those items. |
| Acceptance workload | Handovers spread across draft dates. | Three packages now converge in Week 10. |
| Testing capacity | Additional availability not confirmed. | One team confirmed; competing demand unresolved. |
Next 30 days: two planning cases
Current capacity: sequence packages against the one confirmed team, after the acceptance lead verifies durations.
Additional capacity confirmed: reassess concurrent handovers only after both staffing and package readiness are established. Neither case is a forecast of actual completion.
Questions for the sponsor
- Which package has priority if readiness dates converge?
- Who can confirm test-team availability, and by when?
- Which external commitments depend on acceptance rather than construction completion?
Confidence and limits
Moderate: the close-out records and current staffing plan support the constraint, but final readiness dates and extra team availability are not confirmed.
Evidence register — all records invented
| Record / cut-off | Scenario information | Source quality / limitation |
|---|---|---|
| OC-P9 / Month 2, Day 26 | Two previously open permit items are recorded as closed. | Demo close-out records; no wider permit conclusion. |
| OC-H4 / Month 2, Day 28 | Three work packages target Week 10 acceptance. | Forecast dates; final readiness not verified. |
| OC-T2 / Month 2, Day 28 | One test team is confirmed for Week 10. | Current resource commitment; no assumption about extra capacity. |
Scope, sources, recipients and communication thresholds are agreed for each engagement. These samples illustrate decision support, not a live data service.